See what we did for
BYU Marriott HTHW Tunnel
BYU Marriott HTHW Tunnel
This project includes approximately 1300 LF of High Temperature Hot Water piping in a new utilities tunnel for the Marriott Center, a 23,000 seat basketball arena at BYU.
This project started in June 2009 and was completed in a 6 month time frame. There were two different shutdowns as we needed to tie into two different buildings while maintaining services and still completing our scope of work.
Details
Owner
: Brigham Young UniversityGeneral Contractor
: Big-D ConstructionContract Amount
: $150,000.00Completed
: 2009Address
: Brigham Young UniversityCity
: Provo