See what we did for

BYU Central Utilities Plant


BYU Central Utilities Plant

Central Utilities Plant for Brigham Young University. Renovation required keeping the utilities on line while adding a new HTHW boiler in the existing plant. The duration on this project was over 20 months. A unique aspect of this project was how to handle and put in place the boiler, which was so large it required two cranes to lift and set in place.

Details

  • Owner

    : Brigham Young University
  • General Contractor

    : Layton Construction
  • Contract Amount

    : $6,000,000.00
  • Completed

    : 1993
  • Address

    : Brigham Young University
  • City

    : Provo